AKD Securities
- Hub Power Company (HUBC) has announced that lenders of Thar Energy Limited (TEL) and ThalNova Power Thar (TN) have formally declared Project Completion Date (PCD) for both 330MW Thar-based coal IPPs as of Oct 31, 2025. With PCD achieved, both projects are now eligible to commence dividend payouts, HUBC holds 60% in TEL and 38.3% in TN. Notably, TEL achieved COD in Oct'22, while TNTPL reached COD in Feb'23, compared to the targeted COD date of Mar'21 for both plants.
 
- Notably, we have already incorporated gross dividend assumptions of ~PkR3.0/5.0 per share for both TEL and TNTPL in FY26/27E.
 