Pakistan Railways and ADB Hold 2nd Consultation for $2.5bn ML-1 Project Section

Pakistan Railways, with the support of the Asian Development Bank (ADB), has successfully completed the second pre-market consultation for the Karachi-Rohri section of the Main Line-1 (ML-1) upgradation project. The event attracted 134 participants, including national and international contractors, consultants, and equipment suppliers.

Civil works on the first phase of the project, valued at $2.5 billion, are projected to commence in January 2027. This initial phase covers the 480 km Karachi-Rohri/Sukkur section, which handles approximately 76% of the country's passenger traffic and 98% of its freight traffic.

Project ParameterDetails
Phase 1 Estimated Cost$2.5 Billion
Section Length480 km (Karachi to Rohri/Sukkur)
Expected Construction StartJanuary 2027
Estimated Completion Time2 to 3 Years

The project is expected to be financed majorly by the Asian Development Bank (ADB), with potential co-financing from other institutions including the World Bank, AIIB, IsDB, and EIN.