ISLAMABAD: Federal ministries, divisions, and state corporations have utilized just Rs25.066 billion, or 2.5%, of the total Rs1 trillion Public Sector Development Programme (PSDP) allocation during the first two-and-a-half months of the current fiscal year (FY2026-27).
While the Ministry of Planning authorized Rs211.493 billion (21% of the allocation) and subsequently released Rs92.424 billion, actual spending on the ground has remained sluggish. Underutilization represents only 12% of authorized funds and 27% of released amounts.
| Segment | Total Allocation (Rs Bn) | Authorized (Rs Bn) | Released (Rs Bn) | Utilized (Rs Bn) | Utilization % of Total |
|---|---|---|---|---|---|
| Overall PSDP | 1,000.00 | 211.493 | 92.424 | 25.066 | 2.5% |
| Federal Ministries | 682.486 | 178.277 | 71.233 | 20.905 | 3.0% |
| Corporations | 312.515 | 33.216 | 21.191 | 4.161 | 1.0% |
Investor Takeaway: Extremely slow disbursement and execution of the public sector development budget generally translate into weaker demand for cyclical industrial sectors on the PSX, such as Cement, Steel, and Construction-allied businesses.