Fauji Cement Company Limited (FCCL) has officially approved the installation of Battery Energy Storage Systems (BESS) and dedicated solar power plants at its Nizampur and Jhang Bahtar facilities.
Key project specifications include:
| Component | Total Capacity |
|---|---|
| Battery Storage (BESS) | 50 MWh |
| Solar Power | 10 MW |
The project involves installing 25 MWh of BESS and 5 MW of solar power capacity at each of the two plant sites. The company expects the project to be completed within 10 months. By storing daytime solar energy for discharge during evening peak hours, FCCL aims to optimize its energy costs and reduce reliance on expensive peak-time grid electricity.
Read the full story on the original publisher’s website.
Open original article