Sialkot-Kharian Motorway Delayed to 2028 Over Funding and Land Acquisition Issues

The federal government has informed the Punjab government that construction on the 69-kilometer Sialkot (Sambrial)-Kharian Motorway (M-12) remains significantly delayed, with only 20 percent of the physical work completed so far.

Originally launched in October 2022 with an initial completion deadline of September 2024, the Rs. 89.739 billion project has faced severe hurdles including fund shortages and delays in processing land acquisition gazette notifications by district administrations in Sialkot and Gujrat. Consequently, the deadline has been extended to February 2028.

Project MetricDetails
Total Project CostRs. 89.739 Billion
Total Length69 Kilometers (6 Lanes)
Current Completion Rate20 Percent
Original Completion TargetSeptember 2024
Revised Completion TargetFebruary 2028
ECC Sovereign GuaranteeRs. 27.62 Billion (Aug 2026)

Construction work resumed in February 2026 and includes a major 1,043-meter bridge over the River Chenab. The Economic Coordination Committee (ECC) previously approved sovereign guarantees worth Rs. 27.62 billion in August 2026 to help achieve financial close, while the Prime Minister's Office has called on Punjab authorities to fast-track land acquisition.

Investor Takeaway: Delays in major public infrastructure developments slow down material drawdowns, impacting long-term demand growth for listed construction, cement, and steel suppliers.