Reko Diq Project Production May Face 2-Year Delay to 2030 Amid Security Concerns

OGDC Oil & Gas Development Company Limited
Rs. 312.55 -0.08%
Stock ImpactNegative

Production at the Reko Diq copper-gold project in Balochistan could be delayed by two years to 2030, pending improved regional security and stability in the Middle East, according to government and industry sources.

Barrick Mining Corp., which holds a 50% stake in the multi-billion-dollar project, is reviewing the timeline and expects to resume full-scale development by mid-2027. Despite the slowdown, the company has retained its 700 permanent and roughly 2,000 contractual workers on site.

Parameter / PhaseOriginal EstimateRevised / Current Estimate
Production Target20282030
Phase 1 CapEx$4.0 Billion$5.6 Billion
Phase 2 CapEx$3.5 Billion$3.5 Billion
Total Project CapEx~$7.0 Billion~$9.1 Billion

The remaining 50% equity in the project is equally split between the Balochistan provincial government and three state-owned Pakistani firms: Pakistan Petroleum Limited (PPL), Oil and Gas Development Company Limited (OGDC), and Government Holdings Private Limited.

Investor Takeaway: Capital expenditure for Phase 1 has escalated from $4 billion to $5.6 billion, raising total projected outlay to $9.1 billion. While timeline delays push back initial cash flows for listed partners OGDC and PPL, the long-term viability and projected 37-year free cash flows ($74 billion) remain technically sound.