International Lenders Financing 40 Power Transmission Projects in Pakistan, NA Committee Informed

The National Assembly Standing Committee on Economic Affairs Division, chaired by acting chairman Dr. Mirza Ikhtiar Baig, was informed that international development partners are financing 40 ongoing energy projects under 17 loan agreements.

The key metrics regarding the power transmission projects presented to the committee are summarized below:

Project StatusNumber of ProjectsKey Details & Timelines
Ongoing Projects40Funded by WB, ADB, AFD, KfW, JICA; 52% funds disbursed; completion Nov 2026 – Dec 2028
Proposed Pipeline38Planned infrastructure projects with completion timelines extending up to 2036

Major Implementation Impediments: The committee was apprised of several constraints impacting project timelines, including delayed rupee-cover allocation, Right-of-Way (RoW) disputes, provincial NOC delays (notably for Tarbela 5th Extension and Jauharabad), site access issues, and security concerns in Balochistan (Zhob). Additionally, the CASA-1000 project remains delayed pending completion of its Afghanistan segment.

Investor Takeaway: While long-term transmission upgrades and technologies like STATCOM and BEST-PAK Phase-I aim to improve power grid stability, ongoing execution delays and local counterpart funding constraints continue to hamper prompt project completion.