Pioneer Cement Limited (PSX: PIOC) has signed a contract with Pragmatic Engineering Solutions FZE and China's Sungrow Power Supply Co., Ltd. for the supply and installation of a 15 MW / 30 MWh Battery Energy Storage System (BESS) along with an additional 10 MW solar installation at its Chenki manufacturing facility in District Khushab, Punjab.
The BESS will enable solar energy stored during daytime to be utilized during peak demand hours, helping stabilize grid supply and significantly reducing grid power reliance and energy costs. The project is scheduled for completion by March 31, 2027.
| Project Component | Capacity / Rating |
|---|---|
| Battery Energy Storage System (BESS) | 15 MW / 30 MWh |
| Additional Solar Power Capacity | 10 MW |
Investor Takeaway: Transitioning towards integrated solar and energy storage solutions is expected to lower power generation costs and protect margins from high grid tariffs, delivering long-term efficiency benefits for PIOC.