All 765 kV Transformers Positioned at Mansehra Substation Project

PowerChina's Mansehra Substation Project has successfully completed the positioning of all seven 765-kilovolt (kV) main transformers, marking a major milestone in the construction of Pakistan's first 765/220 kV high-capacity grid station.

The final transformer was placed on November 5, shifting the project into the equipment installation phase. The first transformer unit was positioned on April 17.

ParameterDetails
Total Transformers7 Units (765 kV)
Weight Per Unit225 Tonnes
Shipment Duration344 Days (From Nov 2025)
Completion DateNovember 5, 2026

Once fully operational, the Mansehra Substation will transmit clean hydroelectric power generated from the Dasu Hydropower Project to the national grid and the federal capital, enhancing overall grid stability.