PowerChina's Mansehra Substation Project has successfully completed the positioning of all seven 765-kilovolt (kV) main transformers, marking a major milestone in the construction of Pakistan's first 765/220 kV high-capacity grid station.
The final transformer was placed on November 5, shifting the project into the equipment installation phase. The first transformer unit was positioned on April 17.
| Parameter | Details |
|---|---|
| Total Transformers | 7 Units (765 kV) |
| Weight Per Unit | 225 Tonnes |
| Shipment Duration | 344 Days (From Nov 2025) |
| Completion Date | November 5, 2026 |
Once fully operational, the Mansehra Substation will transmit clean hydroelectric power generated from the Dasu Hydropower Project to the national grid and the federal capital, enhancing overall grid stability.