Pakistan's Reko Diq Project Faces $2.1 Billion Cost Hike and Two-Year Delay

OGDCL OGDCL
View quote —
Stock ImpactNegative

According to a report by the Institute of Cost and Management Accountants (ICMA), Pakistan's Reko Diq project has seen its estimated development cost jump 30 percent to $9.1 billion from $7 billion, while initial production could be delayed by two years to 2030.

The rising price tag increases financial risks for three state-owned enterprises—Oil and Gas Development Company Limited (OGDCL), Pakistan Petroleum Limited (PPL), and Government Holdings (Private) Limited (GHPL)—which have committed around $1.88 billion to the mining venture, holding a collective 25 percent stake.

Project PhasePrevious EstimateNew Estimate
Phase I$4 billion$5.6 billion
Phase II$3 billion$3.5 billion
Total Cost$7 billion$9.1 billion