According to official documents, the estimated cost of 501 federal development projects in Pakistan has surged by over 148% in the past five years. The combined estimated cost escalated by Rs 5.36 trillion, rising from Rs 3.62 trillion to Rs 8.98 trillion, raising strong concerns over project planning, delays, and public fund management.
The Ministry of Water Resources recorded the largest surge, with 34 projects increasing by Rs 2.477 trillion. The National Highway Authority (NHA) followed with 49 projects climbing by Rs 1.401 trillion.
| Ministry / Sector | Projects | Original Cost (PKR) | Revised Cost (PKR) | Increase (PKR) |
|---|---|---|---|---|
| Ministry of Water Resources | 34 | 1.138 Trillion | 3.615 Trillion | 2.477 Trillion |
| National Highway Authority (NHA) | 49 | 1.113 Trillion | 2.514 Trillion | 1.401 Trillion |
| Provinces & Special Areas | 76 | 399 Billion | 1.063 Trillion | 664 Billion |
| Power Division | 34 | 223 Billion | 360 Billion | 137 Billion |
| Higher Education Commission (HEC) | 76 | 159 Billion | 249 Billion | 90 Billion |
| Railways Division | 23 | 177 Billion | 330 Billion | 153 Billion |
| Revenue Division | 5 | 45 Billion | 138 Billion | 93 Billion |
Defense-related developments also saw substantial cost overruns, with 11 projects under the Ministry of Defense surging from Rs 16 billion to Rs 78 billion, and one project under Defence Production rising from Rs 274 million to over Rs 10 billion.
Investor Takeaway: Severe project cost overruns put immense pressure on federal budget allocations and widen fiscal deficits, impacting national economic stability.