AHL Report: Brownfield Refinery Policy amendments notified; 63% reduction in sector FO output expected

AHL Research
Stock ImpactPositive

Pakistan Refinery Sector: Brownfield Policy Amendments

Research House: Arif Habib Limited (REP-300) | Date: September 11, 2026

Key Policy Highlights & Provisions

The Government of Pakistan has notified amendments to the Brownfield Refining Policy 2023 (as of Aug’26). The policy aims to upgrade local refining capacity to Euro-V specifications and drastically reduce surplus Furnace Oil (FO) production.

  • 10% Tariff Protection: Minimum 10% customs/regulatory duty protection on imported MS and HSD for 7 years.
  • Upgrade Agreement (UA): Refineries must sign a legally binding UA with the Petroleum Division within 45 days of notification.
  • Capped Fund Withdrawals: Maximum withdrawal allowed from the Upgradation Account is capped at 24.5% of project cost for used equipment and 27.5% for new equipment.
  • Project Timeline: Upgrades must be completed within 5 years of signing the UA.
  • Non-Compliance Penalty: Refineries failing to sign the UA by October 1, 2026, will see HSD deemed duty reduced to 2.5%, and fully withdrawn by November 15, 2026.

Product Slate Transformation

Post-upgrade, sector-wide Furnace Oil (FO) production is expected to decline by 63%, resolving the long-standing FO overhang capping refinery throughput.

ProductCurrent (Tons/day)Target (Tons/day)Change (%)
Motor Gasoline (MS)10,70218,402+72%
High Speed Diesel (HSD)21,23729,517+39%
Furnace Oil (FO)15,4175,714-63%

Company Positioning & Analyst View

  • Attock Refinery (ATRL): Highlighted by AHL as best positioned to execute the upgrade and capture policy benefits due to lower capex needs, a strong balance sheet, and efficient operations.
  • PRL & Cnergyico (CPL): Expected to undergo the most dramatic product slate transformation, reducing FO output by 81% and 87% respectively.

Key Investment Risks

  • Risk of OGRA license revocation in case of failure to complete project within allowed period.
  • Requirement to submit PKR 1bn unconditional bank guarantee and potential funding delays in reaching financial close.