Mughal Energy (GEMMEL) reports FY26 net profit of PKR 9.13M (EPS: PKR 0.05) vs loss of PKR 21.28M; achieves COD.
Executive Summary
Mughal Energy Limited has reported its financial results for FY26, achieving a net profit of PKR 9.132 million (EPS: PKR 0.05), turning around from a net loss of PKR 21.280 million in FY25. Since the company was in the pre-commencement stage during FY26, operational revenue was zero, and earnings were driven by other income of PKR 80.582 million (rental income & notional property development income). Crucially, subsequent to the year-end, the company successfully achieved Commercial Operation Date (COD) for its 31.50 MW turbine captive hybrid power plant project on August 31, 2026.
Key Highlights & Financial Analysis
- Commercial Operation Date (COD) Achieved: The 31.50 MW main turbine of the 36.50 MW captive hybrid power plant was commissioned on August 31, 2026, marking the start of commercial billing.
- Other Income Boost: Other income jumped to PKR 80.582 million from PKR 8.108 million in FY25, including PKR 42.00 million rental income and PKR 27.44 million notional property development income.
- Administrative & Finance Costs: Administrative expenses rose to PKR 50.292 million (FY25: PKR 25.823M), while finance costs increased to PKR 20.323 million (FY25: PKR 2.775M).
- Asset Expansion: Total assets expanded significantly to PKR 12.015 billion from PKR 7.240 billion, reflecting CWIP investments and coal inventory procurement.
- Breakup Value: Net worth increased to PKR 4.045 billion with a breakup value of PKR 18.67 per share as of June 30, 2026 (FY25: PKR 15.85).
| Financial Metric (PKR Million) | FY26 | FY25 | YoY Change |
|---|---|---|---|
| Revenue | 0.00 | 0.00 | - |
| Other Income | 80.58 | 8.11 | +893.8% |
| Administrative Expenses | 50.29 | 25.82 | +94.8% |
| Finance Cost | 20.32 | 2.77 | +632.5% |
| Profit / (Loss) After Tax | 9.13 | (21.28) | Turnaround |
| EPS (PKR) | 0.05 | (0.11) | Positive |
Risks & Concerns
- Fuel & Commodity Price Volatility: Raw material sourcing risks and international coal price volatility could impact margins following COD.
- Interest Rate Exposure: Increased reliance on long-term and short-term debt exposes the company to variable KIBOR rate fluctuations.
The successful attainment of COD on August 31, 2026 for the main 31.50 MW turbine is a transformative milestone for Mughal Energy. FY27 will mark the company's first full year of operational revenue generation from power supply.